Planning Application - 19/00170/FUL - Adj. 28 Hill Cottage Gardens

Report of the Service Lead, Planning, Infrastructure and Development recommending that the Panel delegate approval in respect of an application for a proposed development at the above address.

Minutes:

The Panel considered the report of the Service Lead, Planning, Infrastructure and Development recommending delegated authority be granted in respect of an application for a proposed development at the above address.

 

Erection of 2x detached dwellings (1x 4-bed, 1x 3-bed) with associated parking and refuse storage (resubmission 18/00190/FUL).

 

Paul King (architect), was present and with the consent of the Chair, addressed the meeting.

 

The presenting officer reported that there was an error on the report and that the recommendation summary should state to grant planning permission subject to criteria listed in the report.  Officers reported that amended plans had been submitted in connection with highway tracking and the public sewer with changes shown to the proposed porch.  In addition that an additional conditions relating to bins and cycle storage needed to be added as set out below.

.

Upon being put to the vote the Panel confirmed the Habitats Regulation Assessment.

 

The Panel then considered the recommendation to delegate authority to the Service Lead: Planning, Infrastructure and Development to grant planning permission. Upon being put to the vote the recommendation was carried unanimously.

 

 

RESOLVED that the Panel:

 

  (i)  confirmed the Habitats Regulation Assessment set out in Appendix 1 of the report.

  (ii)  Delegated authority to the Service Lead – Infrastructure, Planning & Development to grant planning permission subject to the conditions set out in the report and any amendments as set out below and the receipt of: 

a.  a plan showing tracking/revised access;

b.  the planning conditions recommended at the end of this report; and

c.  the completion of a S.106 Legal Agreement or Section 111 agreement to secure either a scheme of measures or a financial contribution to mitigate against the pressure on European designated nature conservation sites in accordance with Policy CS22 of the Core Strategy and the Conservation of Habitats and Species Regulations 2010.

  (iii)  That the Service Lead – Infrastructure, Planning and Development be given delegated powers to add, vary and /or delete relevant parts of the Section 106 agreement or the section 111 agreement and/or conditions as necessary.

 (iv)  In the event that the revised highways plan and/or the legal agreement is not completed within a reasonable period following the Panel meeting, the Service Lead-Infrastructure, Planning and Development be authorised to refuse permission on the ground of failure to secure their provisions.

 

 

 

Additional Conditions

 

26. Refuse & Recycling (Performance)

Before the development hereby approved first comes into occupation, the storage for refuse and recycling shall be provided in accordance with the plans hereby approved and thereafter retained as approved.

REASON: In the interest of visual and residential amenity.

 

Note to applicant: In accordance with para 9.2.3 of the Residential Design Guide (September 2006): if this development involves new dwellings, the applicant is liable for the supply of refuse bins, and should contact SCC refuse team at Waste.management@southampton.gov.uk at least 8 weeks prior to occupation of the development to discuss requirements

 

27. Cycle storage facilities (Pre-Commencement Condition)

Before the development hereby approved first comes into occupation, secure and covered storage for bicycles shall be provided in accordance with details to be first submitted to and approved in writing by the Local Planning Authority. The storage shall be thereafter retained as approved.

REASON: To encourage cycling as an alternative form of transport.

 

 

Supporting documents: