Planning Application - 18/00823/FUL - Thornhill Youth Centre

Report of the Service Lead, Planning, Infrastructure and Development recommending that the Panel delegate approval in respect of an application for a proposed development at the above address.

Minutes:

The Panel considered the report of the Service Lead, Planning, Infrastructure and Development recommending delegated authority be granted in respect of an application for a proposed development at the above address.

 

Redevelopment of the site to provide a three storey building comprising of 12 x 2 bed flats and the erection of 5 x 3 bed houses with associated car parking, bin/refuse, cycle storage and landscaping.

 

Doug Chancellor, Rob Stummer and Barry Cooper (local residents objecting), Kieran Amery (agent), and Councillor Streets (Ward Councillor objecting) were present and with the consent of the Chair, addressed the meeting.

 

Upon being put to the vote the Panel confirmed the Habitats Regulation Assessment.

 

The Panel then considered the recommendation to delegate authority to the Service Lead: Planning, Infrastructure and Development to grant planning permission. Upon being put to the vote the recommendation was carried.

 

RECORDED VOTE to grant planning permission

FOR:  Councillors Savage, Coombs, Claisse and Mitchell

AGAINST:  Councillors L Harris, Murphy and Wilkinson

 

RESOLVED that the Panel:

 

  (i)  confirmed the Habitats Regulation Assessment set out in Appendix 2 of the report.

  (ii)  Delegated approval to the Service Lead – Planning, Infrastructure and Development Manager to grant planning permission subject to the completion of a S.106 Legal Agreement to secure:

a.  Financial contributions towards site specific transport contributions for highway improvements in the vicinity of the site in line with Policy SDP4 of the City of Southampton Local Plan Review (as amended 2015), policies CS18 and CS25 of the adopted LDF Core Strategy (as amended 2015) and the adopted SPD relating to Planning Obligations (September 2013);

b.  Submission of a highway condition survey to ensure any damage to the adjacent highway network attributable to the build process is repaired by the developer.

c.  Either a scheme of measures or a financial contribution towards Solent Disturbance Mitigation Project to mitigate against the pressure on European designated nature conservation sites in accordance with Policy CS22 of the Core Strategy and the Conservation of Habitats and Species Regulations 2010.

d.  Submission of a Training & Employment Management Plan committing to adopting local labour and employment initiatives, in accordance with Policies CS24 & CS25 of the Local Development Framework Core Strategy Development Plan Document - Adopted Version (as amended 2015) and the adopted SPD relating to Planning Obligations (September 2013);

e.  The submission, approval and implementation of a Carbon Management Plan setting out how the carbon neutrality will be achieved and/or how remaining carbon emissions from the development will be mitigated in accordance with policy CS20 of the Core Strategy and the Planning Obligations SPD (September 2013); and

f.  Off-site affordable housing contribution based on the DVS Viability Assessment dated 21st September 2018 in accordance with Policies CS15, CS16 & CS25 of the Local Development Framework Core Strategy Development Plan Document - Adopted Version (as amended 2015) and the adopted SPD relating to Planning Obligations (September 2013).

  (iii)  In the event that the legal agreement is not completed within a reasonable period following the Panel meeting, the Service Lead- Planning Infrastructure and Development be authorised to refuse permission on the ground of failure to secure the provisions of the Section 106 Legal Agreement.

 (iv)  That the Planning and Development Manager be given delegated powers to add, vary and /or delete relevant parts of the Section 106 agreement and/or conditions as necessary.

 