Agenda item

The Boathouse, The Triangle, Cobden Bridge 10/01041/FUL

Report of the Planning and Development Manager recommending delegated authority be granted in respect of an application for a proposed development at the above address, attached.

Minutes:

Redevelopment of the site.  Erection of a part 4, part 5, and part 6-storey building to provide 51 sheltered housing flats for the elderly (36 x one bedroom and 15 x two bedroom units) with associated parking and a riverside walk.

 

Mr Child (Agent), Mr Chapman (Dellwharf Residents Society Limited), Mrs Badham (Police) and Mrs Covall (Local Resident) were present and with the consent of the Chair, addressed the meeting.

 

UPON BEING PUT TO THE VOTE THE OFFICER RECOMMENDATION TO DELEGATE AUTHORITY TO THE PLANNING AND DEVELOPMENT MANAGER TO GRANT CONDITIONAL PLANNING PERMISSION SUBJECT TO THE APPLICANT ENTERING INTO A SECTION 106 LEGAL AGREEMENT WAS CARRIED

 

RECORDED VOTE:

FOR:  Councillors Jones, Mrs Blatchford, Claisse, L Harris, Osmond and Thomas

AGAINST:  Councillor Cunio

 

RESOLVED

 

 (i)

that authority be delegated to the Planning and Development Manager to grant conditional planning approval subject to:-

 

 

 

 

 

 

(a)

the applicant entering into a Section 106 Legal Agreement to secure:

 

 

 

 

i.   Financial contributions towards site specific transport contributions for highway improvements in the vicinity of the site in line with Policy SDP4 of the City of Southampton Local Plan Review (March 2006), Policies CS18 and CS25 of the adopted LDF Core Strategy (2010) and the adopted SPG relating to Planning Obligations (August 2005 as amended);

 

ii.  A financial contribution towards strategic transport projects for improvements in the wider area as set out in the Local Transport Plan and appropriate SPG/D;

 

iii.   Financial contributions towards the relevant elements of public open space required by the development in line with Policy CLT5 of the City of Southampton Local Plan Review (March 2006), Policy CS25 of the adopted LDF Core Strategy (2010) and the adopted SPG relating to Planning Obligations (August 2005 as amended);

 

iv.  Provision of affordable housing in accordance with Core Strategy Policy CS15;

 

v.  Submission and implementation of a Training and Employment Management Plan committing to adopting local labour and employment initiatives in line with Core Strategy Policies CS24 and CS25;

 

vi  Submission of a highway condition survey to ensure any damage to the adjacent highway network attributable to the build process is repaired by the developer;

 

vii  Submission, approval and implementation of a Construction Traffic Management Plan;

 

viii   Dedication of land to public use, construction and maintenance of a public riverside walk;

 

ix    A refuse management plan

 

 

 

(b)

the conditions in the report, the additional conditions below; 

 

 

Additional Conditions

 

31 Age restriction

 

Occupation of the development shall be limited to persons of over 60 years old or where there are two or more persons resident, then at least one person shall be over 60 and the remaining occupants shall be at least 55 years old.

 

REASON:

The Council has had regard to the special circumstances of this residential development in terms of car parking arrangements, amenity space and housing mix as set out in adopted policy CS16 of the Local Development Framework Core Strategy Development Plan Document (January 2010) and is prepared to grant permission on a restricted basis only.

 

32 Highway Construction

 

No development shall take place until details of the means of construction for the part of the building adjoining the public highway in Cobden Avenue, including measures for maintaining the stability of the highway, have been submitted to and approved in writing by the Local Planning Authority. The construction shall be undertaken in accordance with these approved details unless otherwise agreed in writing by the Local Planning Authority

 

REASON:

In the interests of highway safety.

 

REASONS FOR DECISION

 

The development is acceptable taking into account the policies and proposals of the Development Plan as set out below. Other material considerations have been considered, including the scale and form of the proposal, the traffic and parking considerations, safety and security issues associated with the proposed riverside walkway and are not judged to have sufficient weight to justify a refusal of the application, and where applicable conditions have been applied in order to satisfy these matters. The scheme is therefore judged to be in accordance with Section 38(6) of the Planning and Compulsory Purchase Act 2004 and thus planning permission should therefore be granted.

 

Policies - SDP1, SDP 4, SDP 5, SDP 6, SDP7, SDP 8, SDP9, SDP 10, SDP 11, SDP 12, SDP 13, CLT 5, CLT 11, H1, H2 and H7 of the City of Southampton Local Plan Review (March 2006) and Policies CS3, CS4, CS6, CS12, CS13, CS14, CS15, CS16, CS19, CS20, CS23 and CS25 of the Local Development Framework Core Strategy Development Plan Document (January 2010).