Agenda item

Portswood Broadway Next Steps

To consider the report of the Cabinet Member for Environment and Transport detailing the Portswood Broadway consultation and the next steps for the project.

Minutes:

 

DECISION MADE: (CAB 23/24 43623)

 

On consideration of the report of the Cabinet Member for Environment and Transport, Cabinet approved the following:

 

(i)  To note that the Portswood Broadway Transforming Cities Fund scheme second phase of consultation has happened and is used as an opportunity for stakeholders to express their views on the proposal, supported by additional information provided;

(ii)  To note that a “You Said / We Did” response has been prepared for the main themes in the consultation results to assist in shaping a recommendation for the scheme;

(iii)  To note that there is support for the scheme to limit the amount of through route traffic using Portswood Broadway via the use of a bus gate / motor vehicle restriction, accompanied with measures to limit the impact on adjacent streets via an Active Travel Zone;

(iv)  To progress the scheme with the approval for a trial of a part time bus gate / motor vehicle restriction on Portswood Broadway via an Experimental Traffic Regulation Order, with measures to limit the impact on adjacent streets via an Active Travel Zone (ATZ) to be in place ahead of the trial.  Delegation is given to Executive Director Place in consultation with the Cabinet Member Environment and Transport to progress associated detailed design and Traffic Regulation Orders to enable the scheme trial and Active Travel Zone to be delivered;

(v)  To establish a co-design group to inform design decisions for Portswood Broadway to address issues raised from the consultation; and

(vi)  A budget allocation of £500k for the trial is made from the capital programme budget of £2.9M. This budget would be subject to confirmation from the DfT on remaining grant award for the TCF programme.